Date: July 18, 2018

To: Residents of W St Joseph Street

From: Village of Lawrence / Prein&Newhof

Project #: 2170049

Re: W St Joseph Street Resurfacing [80141-129846]

The reconstruction and widening project along W St Joseph Street will begin Monday, July 23.

As part of this project, W St Joseph Street will be widened and the existing road surface will be milled and repaved from the West Village limits to Paw Paw Street. W St Joseph Street will remain open to traffic during the duration of the project.

Schedule:

July 23, 2018: Project begins, sidewalk removals and excavation

August 3, 2018: Westbound widening area paving

August 17, 2018: Eastbound widening area paving

August 19, 2018: Cold milling from West Village limits to Paw Paw Street

August 24, 2018: Paving base and leveling course for entire project

August 31, 2018: Project Completion

Dennis Todd of Prein&Newhof (dtodd@preinnewhof.com) will be the Village’s field

representative during construction. We encourage you to visit the website at

https://www.preinnewhof.com/st-joseph-st/ to track progress and related general information.

Thank you for your cooperation and patience during this construction project.

Should you have any questions regarding any of the specific topics within this notice, please

contact Dan Faulkner at the Village of Lawrence by calling 269-674-8161 or email to

manager@lawrencemi.org.

 